Market TrendsCushman & WakefieldData CentersIndustrial Leasing

Cushman: Data Center Supply Chains Leased 50 Million SF of U.S. Industrial Space Through Q3 2026

Warehouse demand is no longer just e-commerce and 3PLs. Cushman's national count puts servers, switchgear, and cooling gear in the rent roll, with Columbus, Dallas-Fort Worth, and Phoenix doing the heavy lifting.

·8 min read·by David Cartolano·Source: Cushman & Wakefield

Data center-related industrial leasing reached 50 million square feet through Q3 2026, 113% above the full-year 2025 total, Cushman & Wakefield reported November 24, 2026, with the category taking a record 14% of new U.S. industrial leasing in the third quarter.

That is not campus square footage. It is warehouses storing servers, power gear, cooling equipment, construction materials, and replacement parts. Total new industrial leasing rose 21% nationally. The data center slice grew more than five times as fast.

Newmark's 288 million square feet of Q3 leasing told you velocity. Cushman just told you who is in the queue.


Why Did Data Center Tenants Jump to 14% of Q3 Leasing?

Cushman measured tenants occupying 50,000 square feet or more. On that screen, data center-related users accounted for 11% of year-to-date new leasing and 25% of U.S. leases over 1 million square feet signed this year.

The share was 2.0% to 2.5% of national leasing in 2022 and 2023, and roughly 5.0% in both 2024 and 2025. An earlier Cushman study found ecosystem companies took 14.4% of industrial leasing across six major U.S. markets in 2025. That six-market print is not the national 2025 share. Do not mash them.

Jason Price, Head of Americas Logistics & Industrial Research at Cushman & Wakefield, put the physical chain in one paragraph:

Data center development is creating a physical supply chain that extends well beyond the campus itself. Servers, power and cooling equipment, construction materials and replacement parts all have to be manufactured, stored and distributed, and that is now showing up as a meaningful new source of industrial leasing.

The fuel is capacity plus imports. Cushman counted more than 47 gigawatts of operational U.S. data center capacity and another 36 gigawatts under construction. Year-to-date U.S. imports of AI-related equipment, parts, and components rose 62% from a year ago to $659 billion. Those goods move through ports, warehouses, and distribution networks before they hit a hall.


Which Markets Are Absorbing the Supply Chain?

3PL leasing tied to data center users reached nearly 11 million square feet year to date across 10 transactions greater than 500,000 square feet. Cushman tied that volume to long-term contracts announced earlier this year between major 3PLs and leading hyperscalers. Activity has been particularly strong in Columbus, Dallas-Fort Worth, and Phoenix.

Hyperscalers also signed six new leases in the same size segment to store and distribute equipment, parts, and components, concentrated in Dallas-Fort Worth, Atlanta, Kansas City, and Charlotte.

A secondary read of the report by The AI Consulting Network, published November 25, 2026, added a tenant mix Cushman's release did not print: manufacturers 31%, construction and building suppliers 30%, 3PLs 20%, data center users themselves 15%, and other tenants 4%. Treat that split as one analyst's summary of the report, not the press release. The same recap said Columbus, Phoenix, Atlanta, and Dallas-Fort Worth together produced more than 32 million square feet of this leasing, and that data center-related users account for 22% to 41% of year-to-date leasing in Phoenix, Columbus, Kansas City, Virginia, and Dallas-Fort Worth.

That geography matches Link Logistics saying 15% of new leasing is data-center-related. Brandon Page's rule of thumb was about 2 million square feet of industrial demand per gigawatt. Multiply Cushman's 36 gigawatts under construction and you get a spillover order of magnitude, not a lease-by-lease forecast.


How Durable Is This Demand Once Campuses Open?

Cushman is explicit: most data center-related industrial leasing is likely to be sustainable because campuses still need maintenance and the distribution of equipment, parts, and components.

The risk sits in the build-phase slice. If construction and building suppliers are 30% of volume, as the secondary recap said, that is about 15 million square feet whose space need is most tightly tied to campuses being built. A three-year staging lease that expires when the nearby hall opens is not the same credit as a ten-year 3PL contract behind a hyperscaler.

Price also flagged a timing advantage that conventional occupiers do not have. Data center-related users often know where new campuses will be developed before ground is broken and can secure space early. In those hubs, hyperscalers, suppliers, and 3PLs are another bidder for Class A.

Occupiers with requirements in major data center hubs may want to evaluate their space needs and timelines earlier. With new supply expected to remain modest in the near term, occupiers can secure well-located, Class A facilities.

If you are a food, auto-parts, or regional 3PL user in Phoenix or Columbus, you are now competing with people who saw the substation queue first.


What Should Occupiers Do in Data Center Hubs?

Move the requirement forward. Cushman said the industrial under-construction pipeline has risen year over year in Columbus (190%), Atlanta (171%), Nashville (110%), Phoenix (92%), and Chicago (68%). Those jumps look large. The firm also said pipelines remain well below 2023-2024 highs, and new supply is expected to stay modest in the near term.

That combination is the squeeze: demand is concentrated, starts are up from a trough, and near-term deliveries are still thin. Advanced manufacturing and data center-related tenants are expected to lift absorption nationwide into 2027.

JLL already put data-center suppliers at 14.7% of recent leasing, clustered in Dallas-Fort Worth and metro Washington. Cushman's national 14% Q3 share is the confirmation, not a new religion. Owners should tag the rent roll for equipment distributors, electrical and cooling vendors, and 3PLs on hyperscaler contracts. If that bucket is 20% or more of NOI in a hub market, your exit cap now has a single-industry overlay.

David Cartolano covers these industrial tapes for Your CAIO. The useful test is whether the tenant's business survives after the nearest campus is energized.


How Does Cushman's Count Compare With Other Brokers?

Brokerages do not share a tape. They share a direction.

SourcePrintWhat it measures
Cushman (Nov 24)50 million SF YTD; 14% of Q3 leasingData center-related users, 50,000 SF+ tenants
JLL (via Facilities Dive)14.7% of recent leasingConstruction-material and fixture tenants serving hyperscale
Link / FreightWaves (Nov 20)15% of new leasingOne owner's last-mile book
Newmark (Nov 13)288 million SF Q3 leasing; Class A 51.6%National velocity; quality mix
Cushman 2025 six-market14.4%Six markets only, not national

50 million square feet through three quarters, against an implied ~23.5 million square feet for all of 2025 (50 divided by 2.13), means the category has already added more than last year's entire print. That is the citable fact. Do not convert it into net absorption. Leasing is velocity. Absorption is occupancy.


The Numbers Worth Writing Down

  • 50 million SF: data center-related industrial leasing through Q3 2026
  • 113% above full-year 2025; total new industrial leasing +21%
  • 14% of Q3 new leasing (record); 11% YTD
  • 25% of U.S. leases over 1 million SF
  • Share history: 2.0% to 2.5% (2022-23), ~5.0% (2024-25)
  • 47 GW operational; 36 GW under construction
  • AI-related imports: +$62% to $659 billion
  • 3PL DC-tied leasing: ~11 million SF, 10 deals >500,000 SF
  • Pipeline YoY: Columbus +190%, Atlanta +171%, Nashville +110%, Phoenix +92%, Chicago +68%

The Campus Is Not the Whole Building Program

50 million square feet is the first national warehouse number that treats AI infrastructure as a logistics tenant, not a power-market anecdote. The halls still matter. So do the boxes that feed them.

If you own powered Class A in Columbus, Dallas, or Phoenix, this is a hold and mark tape. If you are a conventional occupier in those same submarkets, Cushman's advice is operational: get in line before the 3PL with the hyperscaler contract does.


Sources

Frequently Asked Questions

How much U.S. industrial space did data center-related tenants lease through Q3 2026?

Cushman & Wakefield counted 50 million square feet through the third quarter of 2026, 113% above the full-year 2025 total. That growth far outpaced a 21% increase in total new industrial leasing nationally, according to the November 24, 2026 release.

What share of Q3 2026 industrial leasing was data center related?

Data center-related users accounted for a record 14% of new industrial leasing in Q3 2026 among tenants occupying 50,000 square feet or more. Their year-to-date share was 11%, and they signed 25% of U.S. leases larger than 1 million square feet this year.

Which markets are seeing the most data center warehouse demand?

Cushman said 3PL activity tied to hyperscalers has been particularly strong in Columbus, Dallas-Fort Worth, and Phoenix. Hyperscalers also signed six leases larger than 500,000 square feet to store equipment, parts, and components, concentrated in Dallas-Fort Worth, Atlanta, Kansas City, and Charlotte.

Is this warehouse demand only a construction-phase spike?

Cushman expects most of the leasing to prove durable because operating campuses still need parts, maintenance, and distribution. The firm also cautioned that occupiers in major data center hubs should secure Class A space earlier, because new supply is expected to stay modest in the near term.

How does Cushman's 14% compare with other brokers?

JLL previously attributed 14.7% of recent leasing to construction-material and building-fixture tenants serving data centers. Link Logistics said 15% of its new leasing over the past year was data-center-related. Cushman's 14% is a national Q3 share, not a six-market 2025 print.