# Dwight Capital Closes $42 Million HUD 221(d)(4) for Cheferkon's 184-Unit One Salem

> Brandon Baksh originated the debt. Co-founder Greg Chew said phased delivery starting in the third quarter of 2027 lets lease-up income offset financing costs. The Lilburn, Georgia, sponsor's first North Carolina ground-up sits four miles south of Wake Forest University on 15 acres.

- URL: https://www.yourcaio.co/news/cheferkon-dwight-capital-42-million-one-salem-november-2026
- Published: 2026-11-14
- Author: David Cartolano (https://www.yourcaio.co/about)
- Category: Acquisitions
- Property type: Multifamily
- Tags: Dwight Capital, Cheferkon Partners, HUD 221(d)(4), Winston-Salem, One Salem Apartments
- Source: [Commercial Observer](https://commercialobserver.com/2026/11/dwight-capital-cheferkon-north-carolina-apartments-wake-forest/)

## Key Takeaways

- Dwight Capital originated a $42 million HUD 221(d)(4) construction loan for Cheferkon Partners' 184-unit One Salem Apartments in Winston-Salem, N.C., Commercial Observer reported November 13, 2026.
- The nonrecourse loan is structured with a fully amortizing 40-year term; Chew separately said the rate is locked at 5.43% fixed, with construction converting to permanent debt at stabilization.
- The garden community will sit at 4033 Vestmill Road on 15 acres, about four miles south of Wake Forest University and about 10 minutes from downtown Winston-Salem.
- Eight buildings will hold one- to three-bedroom units plus detached garages, with full completion slated for 2028 and the first building targeted for the third quarter of 2027.
- The $42 million mortgage equates to about $228,000 per unit and is Cheferkon's first North Carolina ground-up after Atlanta-area work from its Lilburn, Georgia, base.

**Dwight Capital originated a $42 million HUD 221(d)(4) construction loan** for **Cheferkon Partners'** planned **184-unit** One Salem Apartments in Winston-Salem, N.C., **Commercial Observer reported November 13, 2026**. The site is **4033 Vestmill Road**. Full completion is slated for **2028**.

That is about **$228,000 a unit** of FHA-insured, nonrecourse, 40-year money on a garden community four miles south of Wake Forest University. [NAHB's Multifamily Production Index is sitting at 41](https://www.yourcaio.co/news/nahb-multifamily-mpi-41-moi-69-q3-2026-november-2026). Someone still closed HUD construction debt in the Carolina Piedmont. The structure is why.

---

## What Did Dwight Capital Fund at One Salem?

Brandon Baksh originated the HUD 221(d)(4) loan for a Cheferkon-led investment group. Commercial Observer described the debt as **nonrecourse** with a **fully amortizing 40-year term**, which Dwight said is meant to give the borrower long-term stability and predictable debt service. Greg Chew, who co-founded Cheferkon with Raihan Ferdous, separately said the loan is a **single-close** construction facility that converts to a 40-year permanent loan at stabilization, **locked at 5.43% fixed** for the life of the loan, fully assumable subject to HUD and lender approval, and eligible for in-place interest-rate reductions if market rates fall.

The physical program is a garden-style complex on **15 acres**: **eight buildings**, one- to three-bedroom units, detached garages. Amenities listed by Commercial Observer are a clubhouse, fitness center, business center, swimming pool, barbecue stations, a pickleball court, and a dog park. Chew put the location about **10 minutes** from downtown Winston-Salem, with Walmart and Target nearby and Wake Forest University as a demand driver.

| Item | Figure |
|------|--------|
| HUD 221(d)(4) loan | $42 million |
| Units | 184 |
| Debt per unit | ~$228,000 |
| Site | 4033 Vestmill Road, 15 acres |
| Buildings | 8 garden buildings |
| First building | Q3 2027 (target) |
| Full completion | 2028 |
| Coupon (Chew) | 5.43% fixed |

Cheferkon is based in Lilburn, Georgia. Commercial Observer said One Salem is the firm's **first North Carolina ground-up** after Atlanta-area work. Ferdous said the investment group has **five other partners** and that Cheferkon is looking to add more by year-end. [Acento's $48 million buy of 395-unit Legacy at West Cobb in Marietta](https://www.yourcaio.co/news/acento-legacy-west-cobb-48-million-marietta-november-2026) is the other Georgia-adjacent tape this month: existing suburban product, short-term acquisition debt. One Salem is the opposite trade, long HUD paper on unbuilt doors.

---

## Why HUD 221(d)(4) Instead of Bank Construction Debt?

Section 221(d)(4) is FHA-insured financing for new construction or substantial rehabilitation of multifamily. 2026 lender term sheets describe the standard box: interest-only during construction, then **40 years fully amortizing**; **nonrecourse** in both phases; **87% loan-to-cost** and **1.15x DSCR** on market-rate deals; **0.25%** mortgage insurance premium; Davis-Bacon wages; and a loan that is **assumable** with HUD and lender approval. Lument and Arbor both publish that grid. It is the program Dwight used.

Bank construction debt is usually recourse, floating or short-fixed, and needs a takeout. HUD 221(d)(4) is the takeout on day one. Chew's phased lease-up point only works because the perm is already locked:

> "We have an anticipated lease-up schedule as soon as the buildings start coming online. That starts to build up income, and that helps offset some of the financing costs."

- **Greg Chew, Co-Founder, Cheferkon Partners, to Commercial Observer, November 13, 2026**

A 5.43% 40-year coupon is not cheap versus 2021 money. It is cheap versus a three-year construction loan that still needs a 2028 refi. HUD is the lock. Applications typically run two stages, with market study, appraisal, Phase I, and architectural cost review. Chew called it one of the most document-intensive financing processes in the business. The $42 million close is the proof they finished it. Anyone comparing this basis to a bank deal has to add Davis-Bacon, MIP, and HUD inspection, then subtract the missing personal guarantee and the missing takeout risk.

---

## What Does the Winston-Salem Demand Story Look Like?

Chew's pitch to Commercial Observer was limited supply, a 10-minute downtown drive, big-box retail, and Wake Forest. That is a university-and-employment garden thesis. CBRE's Q3 2026 national print had U.S. rent at **$2,268**, deliveries down **11%** to **85,300** units, and vacancy at **4.7%**. National averages do not price Winston-Salem. They do tell you new garden product is arriving into a slower delivery tape.

NAHB's garden/low-rise MPI component is **46**, below break-even, while the occupancy index for garden product is still **70**. Developers feel poor about starting; owners still feel decent about filling. One Salem is a start. The bet is that a 2027-2028 Triad lease-up looks more like that occupancy gauge than the production gauge.

One Salem is eight garden buildings on 15 acres with the first stack in Q3 2027 and a 2028 finish. Chew's "limited supply" claim is sponsor color, not a CoStar table in the Observer story. What is documented is Vestmill Road, 184 units, and that delivery window.

---

## How Does Phased Delivery Change Lease-Up Risk?

Eight buildings with a first delivery in Q3 2027 and a 2028 finish is a two-year lease-up, not a single certificate of occupancy. HUD 221(d)(4) is built for that: interest-only in construction, then conversion. Income from building one starts to carry remaining interest as buildings two through eight rise.

[ALN's October 2026 concession survey](https://www.yourcaio.co/news/aln-lease-concessions-30-percent-october-2026-november-2026) is the risk tape. **Sixty percent** of lease-up properties offered incentives, averaging **6.4 weeks** free. National concession availability hit **29.7%**, a decade-plus high. A 184-unit garden community opening into that environment should budget weeks on the house, not just a 5.43% constant.

Phasing helps because you are not dumping 184 units on one weekend. It hurts because you are leasing against your own remaining construction. Chew's offset-the-financing-costs line only works if building one actually leases. Wake Forest, downtown adjacency, and detached garages are the demand arguments. Pickleball and a dog park are table stakes.

Ferdous said Cheferkon wants more partners by year-end. HUD can go to 87% of cost on market-rate 221(d)(4); the rest is equity and reserves. Commercial Observer did not print total cost. What is reported is the debt, the unit count, and a sponsor still raising.

---

## The Numbers Worth Writing Down

- **Loan:** **$42 million** HUD 221(d)(4)
- **Units:** **184** (~**$228,000** per unit)
- **Address:** **4033 Vestmill Road**, Winston-Salem, **15 acres**
- **Buildings:** **8**, one- to three-bedroom, detached garages
- **Rate (Chew):** **5.43%** fixed, 40-year amortization, nonrecourse
- **First building:** **Q3 2027**; **full completion 2028**
- **Sponsor:** Cheferkon Partners (Lilburn, Ga.), first North Carolina ground-up
- **Originator:** Brandon Baksh, Dwight Capital

---

## Long HUD Paper Is the Point

A Georgia sponsor taking 40-year FHA debt into Winston-Salem is a rate-and-recourse decision, not a trophy-market decision. $42 million at 5.43% with no personal guarantee, converting from construction to perm without a 2028 refi, is the product bank desks are not matching. The risk is a phased lease-up into a market where 60% of lease-ups are already giving weeks away.

If the first building opens in Q3 2027, Cheferkon will have used the program as designed. If it slips, the 40-year coupon still beats a floating construction line, and the guarantee still is not personal. That is why 221(d)(4) closes when MPI is 41. [David Cartolano](https://www.yourcaio.co/about) will watch whether that first stack actually delivers, because the loan is done and the lease-up is not.

---

## Sources

- [Dwight Capital Lends $42M on North Carolina Apartments Build](https://commercialobserver.com/2026/11/dwight-capital-cheferkon-north-carolina-apartments-wake-forest/), Commercial Observer, November 13, 2026
- [Greg Chew on the One Salem HUD 221(d)(4) closing](https://www.linkedin.com/posts/gregorychew_commercialrealestate-multifamilydevelopment-activity-7522003748576059395-noQ7), LinkedIn
- [HUD 221(d)(4) and 220 Multifamily Construction term sheet](https://www.lument.com/loan-term-sheets/fha-hud-221d4-section-220-multifamily-new-construction-substantial-rehabilitation/), Lument
- [FHA 221(d)(4) term sheet](https://arbor.com/wp-content/uploads/2025/04/FHA-221d4-022526.pdf), Arbor
- [U.S. Multifamily Rents Edge Higher in Q3 2026 as Construction Slows](https://www.cbre.com/press-releases/us-multifamily-rents-edge-higher-q3-2026-construction-slows), CBRE, November 4, 2026

## Frequently Asked Questions

### How large is the Dwight Capital loan for One Salem Apartments?

Dwight Capital originated a $42 million HUD 221(d)(4) construction loan for the 184-unit Winston-Salem project, Commercial Observer reported November 13, 2026. Brandon Baksh originated the nonrecourse debt. At $42 million on 184 units, the loan is about $228,000 per apartment.

### Where is One Salem Apartments being built?

The site is 4033 Vestmill Road in Winston-Salem, North Carolina, a 15-acre parcel about four miles south of Wake Forest University and about 10 minutes from downtown. Commercial Observer, reporting November 13, 2026, said nearby retailers include Walmart and Target.

### When will One Salem Apartments open?

Cheferkon is targeting full completion in 2028 and hopes to finish the first of eight buildings in the third quarter of 2027. Co-founder Greg Chew told Commercial Observer that buildings will lease as they come online so income can offset financing costs during the remaining construction period.

### What are the HUD 221(d)(4) terms on this deal?

Commercial Observer described nonrecourse, fully amortizing 40-year HUD 221(d)(4) debt. Chew said the loan is a single-close construction-to-permanent structure locked at 5.43% fixed, fully assumable subject to HUD and lender approval. Program term sheets typically cap market-rate loans at 87% of cost with a 1.15x DSCR.

### Who is developing One Salem Apartments?

Cheferkon Partners, based in Lilburn, Georgia, and co-founded by Greg Chew and Raihan Ferdous. Ferdous told Commercial Observer the investment group has five other partners and that Cheferkon is looking to add more by year-end. It is the firm's first North Carolina ground-up.

---

Cite as: David Cartolano, "Dwight Capital Closes $42 Million HUD 221(d)(4) for Cheferkon's 184-Unit One Salem," YourCAIO.co, 2026-11-14, https://www.yourcaio.co/news/cheferkon-dwight-capital-42-million-one-salem-november-2026